Redondo Beach Harbor Commission rejects city council’s Seaside Lagoon plan
By Garth Meyer
by Garth Meyer
Plans for Seaside Lagoon may be in a holding pattern after the Redondo Beach Harbor Commission voted Tuesday to send a note of caution to the city council.
Tasked to advise the council on plans they are set to go ahead with, the Harbor Commission said it would not support the city’s current design, asked that any work done should align with projected 2050 sea levels, advised the council to seek an extension for a $10 million State Parks grant, and requested that Lagoon plans be re-opened to find further ideas for the 65-year-old public park.
In conclusion, the motion by veteran harbor commissioner Roger Carlson, and amended by Jamie Waryck, asked that any new design focus on amenities usable year-round.
“If you do go ahead and ignore us, please consider these factors,” Carlson said.
Finally, the motion noted that the Harbor Commission would put on its Oct. 14 agenda a presentation by BeachLife Festival and California Surf Club co-founder Allen Sanford about building a wave pool as part of Seaside Lagoon.
The evening began with context.
Michelle Pinedo, community services manager, reported that Seaside Lagoon has totaled 50,200 visitors so far in 2026, including 100 camps/reserved spaces, in its yearly season running from Memorial Day weekend to Labor Day.
Since 2001, the city has paid $935,000 in state fines and S.E.P. – Supplemental Environmental Projects – costs due to non-compliant water discharge into the ocean, stemming from its original, antiquated system, once tied to the AES power plant.
Marc Wiener, Redondo Beach community development director, explained that to move ahead on the city’s existing plan for Seaside Lagoon, it would only need a Coastal Development permit, and that the Harbor Commission’s role is just advisory.
The city council needs to apply for the permit.
The current plan for the Lagoon would, in Phase 1, add more open sand space, new restrooms and convert the wading pool from saltwater to chlorinated freshwater; a sand-entry pool with a concrete bottom. Phases Two and Three would feature a new Lagoon entryway, more landscaping, cabanas, more new restrooms and showers, fire pits, volleyball courts, picnic areas and a playground.
The Aug. 25 Harbor Commission special meeting was “really just (because of) the timeline,” Wiener said. “Trying to get that (application) into Coastal as soon as we can.”
The city council has aimed to have the Lagoon project done by the 2028 Olympics, in order for it to be available to be used for events such as watch parties.
On Tuesday evening, after an opening presentation from Elizabeth Hause, Redondo Beach community services director, and consultant Perry Cardoza, Nuvis Landscape Architecture president, Commissioner Carlson asked Cardoza a series of questions about how the new wading pool system would function.
“We’re still fine-tuning the mix for the concrete bottom so it doesn’t float,” Perry said as part of one response.
“Today we’re fighting water quality issues and tomorrow we’re fighting sand-clogging issues,” Carlson said of his concerns.
He asked about sea level rise and questioned if the city will have the money to maintain the new pool infrastructure.
“Right now, it doesn’t seem like the city can keep the shower working,” he said.
“We will do what we can, within the budget and manpower, as always,” Hause said.
“The city budget hasn’t come back as I’d hoped,” Carlson said of post-pandemic numbers. “Fresh water, that’s a big knock (as opposed to saltwater), reduced scope, minimal cost, do it in phases. It’s disappointing.”
“We’re a little past 30% in our drawings,” Cardoza said. “There’s still some design development (to do).”
Finally, Carlson announced, citing sea level rise, “I’m not voting for this.” He said he was ready to make a motion to deny the project right then “and we’ll all go home in time for dinner.”
“I too am quite disappointed,” said Commissioner Tom Bauer. “That we’re not taking into account sea level rise is pretty stunning.”
He asked more questions about sea level rise and what weather incidents the system is expected to be able to handle.
“We’ll get more information before (it goes to) city council,” Hause said.
Wiener noted that the Coastal Commission generally does not approve of sea walls.
“I’m hearing disconnects in the details,” said Commissioner Leslie Chrzan.
“It’s a smaller scope, smaller project,” Cardoza said to a question from her.
“Those aren’t really specific words,” Chrzan said.
Head Harbor Commissioner Ryan Abelman said he did not disagree with what his fellow commissioners said, but made a point that the city “has to please everybody… and do this all on limited funds.”
“(Nonetheless) it’s taking a step. It’s changing the character of Seaside Lagoon,” Abelman said. “Essentially this is no different than (a pool), like what other communities have… We have to determine if what’s before us is worth moving forward, and potentially losing X million dollars. Is that accurate?”
“Yes,” Hause said.
Commissioner Lee Coller followed with his input.
“I pretty much agree with everything that’s been said here.”
He asked for further attendance numbers and Pinedo said the average this summer is 1,200 people on a weekday, including camps, etc., and 1,200 – 2,000 on weekends.
“I also pretty much agree with everything said,” said Harbor Commissioner Lisa Falk. “This isn’t what I thought we were getting. I thought we would be designing for 2050. Are we?”
“Our determination from our design team was to design for now, not 2050,” Cardoza said.
“What you just said is one of my biggest concerns,” said Commissioner Waryck. “We’re looking for the highest and best use of Seaside Lagoon, while respecting the history. I’m not seeing that here. I feel like this is a temporary Band-Aid that we can’t undo. We have to do this one time.”
Chrzan asked for more information on operation and maintenance costs.
“It just feels negligent to move forward with all these loose details,” she said.
Public comment began with Dinah Lary calling for a wave pool to be considered. Jeff Joncs, president of the King Harbor Association – and Qualify Seafoods president – asked for additional revenue, visitors and tourism to be taken into account.
“Increase the city budget through what we do down there,” he said.
Chris Brown, California Surf Club creative director, also requested consideration of a wave pool.
“People are willing to pay to surf… (you) could use that money to keep Seaside Lagoon open all year,” he said.
A woman on Zoom countered, saying, “This is not to be laid at the feet of” Seaside Lagoon, the public park. “It’s not about profits, it’s about community… And not privatizing this beautiful park that we have.”
Allison Hales from Culture Club South Bay expressed opposition to the current city plan and said, “A wave pool is really exciting for us.”
Another commenter questioned whether a wave pool could effectively fit in Seaside Lagoon, and not take up too much of the original wading pool.
“If they want to expand it into the parking lot, I might support that,” she said.
Tom Horton, South Bay Boardriders president and co-founder, went to the podium and gave his support for a wave pool.
Mara Santos, Redondo Beach Chamber of Commerce president, said that the business community has not had enough input on the project, and recommended that the city council pause it.
Then Allen Sanford went up and spoke. He spent his own money this spring to hire a San Diego wave pool-design firm to illustrate what the possibility could be here.
“I want to apologize for potentially being an obstacle,” Sanford said, noting that he was speaking from strong familiarity with the Lagoon, seeing it every day from the BeachLife office in a wing of the Sonesta Hotel across the street.
Sanford read a line in the city staff report about Lagoon plans.
“It also wouldn’t increase parking demand…” he read.
“Tonight’s not about the wave for me. There is a better way to do this. I know there’s a better way to do this.”
A total of seven e-comments came in, supporting the city’s plan.
As it stood Tuesday night, the Harbor Commission’s duty was to make a recommendation to the city council, which councilmembers will now consider in September, and may refer it back to Harbor Commission for more discussion.
“2050 is only 24 years away. It’s not that long,” Harbor Commissioner Coller said.
“The only reason we’re considering this design is because of money. And lack of money,” said Chzar.
Commissioner Carlson harkened back to the work of the 2021-22 Waterfront Amenities Commission, which he was part of, when a wave pool was brought up. He argued against it then, saying it was not feasible, while other members such as Mark Hansen wanted to explore it further. Carlson said the technology has advanced since then, and it has also been proven that events on the waterfront could draw significant crowds.
“We’ve seen that investment in the area does work. We know that now,” Carlson said, giving a final round of comments.
“Are we building something that’s going to get people there on a cold Tuesday in February?”
“I’m also tired of low-cost amenities not well-cared for.”
“It’s financially irresponsible not to hear more about the wave pool, which could dramatically bring more funds.”
The State Parks grant, given specifically for Seaside Lagoon at the behest of State Senator Ben Allen, expires in June 2028.
It is eligible to be expanded from one to three years. ER